Back to projects

Fire Hall - Three Hills

Three Hills, Alberta

completeAdministration, Emergency and Public WorksISF
Federal contribution
$650,000
Federal share33%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Three Hills
Construction start
Jul 15, 2009(actual)
Construction end
Jun 25, 2010(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jul 1, 2009
  • Construction end2 months earlyforecast Aug 31, 2010

Also in Three Hills