Twin Arenas and Curling Club Modernization
Federal contribution
$1.2M
$1,155,684
Federal share33%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 21, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Whitecourt
- Construction start
- May 1, 2010(actual)
- Construction end
- May 13, 2011(actual)
Against the original forecast
- Construction start8 months lateforecast Aug 31, 2009
- Construction end4 months lateforecast Dec 31, 2010
Also in Whitecourt
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26118 in the federal list. How to read these figures.