Cessford and District Water Line
Federal contribution
$1.2M
$1,169,116
Federal share33%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 21, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Special Areas Board 2,3,4
- Construction start
- Jul 11, 2010(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start9 months lateforecast Oct 9, 2009
- Construction end7 months lateforecast Sep 1, 2010
Also in Hanna
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26126 in the federal list. How to read these figures.