Henry Kroeger Water Treatment Plant Generator Upgrade
Federal contribution
$407,643
Federal share49%
of $833.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2017
2018
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Henry Kroeger Regional Water Services Commission
- Construction start
- Oct 12, 2017(actual)
- Construction end
- Nov 30, 2018(actual)
Against the original forecast
- Construction start2 weeks lateforecast Sep 27, 2017
- Construction end4 months earlyforecast Mar 31, 2019
Also in Hanna
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49915 in the federal list. How to read these figures.