5th St SE Connection
Federal contribution
$3.0M
$2,988,948
Federal share33%
of $9.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 21, 2009
201020112012201320142015
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of High River
- Construction start
- Aug 31, 2010(actual)
- Construction end
- Jun 30, 2015(actual)
Against the original forecast
- Construction start5 months lateforecast Apr 1, 2010
- Construction end4.6 years lateforecast Nov 15, 2010
Also in High River
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26152 in the federal list. How to read these figures.