Grading of Highway 58, Garden River Road: East of Wentzel River to Wood Buffalo Park Boundary

High River, Alberta

completeHighways and RoadsISF
Federal contribution
$2.3M
$2,291,750
Federal share25%

of $9.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 2, 2009
ApprovedJul 23, 2010
20102011
Built

Approved 14 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Aug 1, 2010(actual)
Construction end
Oct 20, 2011(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Aug 15, 2010

Also in High River