HKRWSC Water Treatment Plant Clarifier Upgrade
Federal contribution
$150,000
Federal share32%
of $471.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 21, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Village of Cereal
- Construction start
- Jan 17, 2011(actual)
- Construction end
- Sep 12, 2011(actual)
Against the original forecast
- Construction start8 months lateforecast May 15, 2010
- Construction end12 months lateforecast Sep 15, 2010
Also in Cereal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26173 in the federal list. How to read these figures.