HKRWSC Sheerness Pump House Emergency Generator & MCC

Cereal, Alberta

completeDrinking WaterCC Top Up
Federal contribution
$213,782
Federal share33%

of $641.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 21, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Village of Cereal
Construction start
Jan 10, 2011(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start8 months lateforecast May 15, 2010
  • Construction end14 months lateforecast Sep 15, 2010