Provident Place Phase IV Renovation
Federal contribution
$454,666
Federal share33%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 21, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Redwater
- Construction start
- Jun 25, 2010(actual)
- Construction end
- Jul 19, 2011(actual)
Against the original forecast
- Construction start4 months lateforecast Mar 1, 2010
- Construction end9 months lateforecast Nov 1, 2010
Also in Redwater
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26185 in the federal list. How to read these figures.