Town of Redwater Downtown Storm Sewers
Federal contribution
$597,473
Federal share25%
of $2.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Redwater
- Construction start
- Apr 26, 2010(actual)
- Construction end
- Mar 22, 2011(actual)
Also in Redwater
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34607 in the federal list. How to read these figures.