Aberdeen Rural Water Pipeline
Federal contribution
$3.1M
$3,095,954
Federal share33%
of $9.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2009
201020112012
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Highway 41 Water Utility
- Construction start
- Oct 19, 2009(actual)
- Construction end
- May 12, 2012(actual)
Against the original forecast
- Construction start6 months earlyforecast May 1, 2010
Also in Aberdeen
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26310 in the federal list. How to read these figures.