Town of Aberdeen - Water Pumphouse, Reservoir and Pump Upgrades

Aberdeen, Saskatchewan

underwayDrinking WaterGIS
Federal contribution
$1.4M
$1,366,000
Federal share40%

of $3.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 28, 2024
202420252026
BuiltForecast

Approved 9 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Aberdeen
Construction start
Apr 15, 2025(actual)
Construction end
May 31, 2026(forecast)

Against the original forecast

  • Construction start23 months lateforecast May 1, 2023