Town of Aberdeen - Water Pumphouse, Reservoir and Pump Upgrades
Federal contribution
$1.4M
$1,366,000
Federal share40%
of $3.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 28, 2024
202420252026
BuiltForecast
Approved 9 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Aberdeen
- Construction start
- Apr 15, 2025(actual)
- Construction end
- May 31, 2026(forecast)
Against the original forecast
- Construction start23 months lateforecast May 1, 2023
Also in Aberdeen
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67490 in the federal list. How to read these figures.