completeCultureCC
Federal contribution
$94,533
Federal share33%

of $283.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 4, 2009
201020112012
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Montague
Construction start
Jul 18, 2011(actual)
Construction end
Apr 30, 2012(actual)

Against the original forecast

  • Construction start15 months lateforecast Apr 10, 2010
  • Construction end4 months lateforecast Dec 31, 2011