Various System Upgrades

Rexton, New Brunswick

completeWastewaterCC
Federal contribution
$342,375
Federal share33%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
20102011201220132014
Built

Approved 7 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Village of Rexton
Construction start
Sep 6, 2011(actual)
Construction end
Mar 31, 2014(actual)

Against the original forecast

  • Construction start24 months lateforecast Sep 15, 2009
  • Construction end7 months lateforecast Aug 31, 2013

Also in Rexton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26368 in the federal list. How to read these figures.