Route 116 - to Rexton village limits

Rexton, New Brunswick

completeHighways and RoadsISF
Federal contribution
$1.1M
$1,137,287
Federal share50%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 12, 2009
ApprovedJul 28, 2010
2010
Built

Approved 14 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of New Brunswick
Construction start
Aug 17, 2009(actual)
Construction end
Oct 23, 2009(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jul 31, 2009

Also in Rexton