Bouyer Creek Municipal Wellfield

Stratford, Prince Edward Island

completeDrinking WaterCC
Federal contribution
$714,599
Federal share27%

of $2.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 4, 2009
2010201120122013
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Stratford
Construction start
Sep 17, 2012(actual)
Construction end
Oct 18, 2013(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 1, 2012
  • Construction end9 months lateforecast Jan 13, 2013

Also in Stratford

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26480 in the federal list. How to read these figures.