North Rustico Well Site Upgrades

North Rustico, Prince Edward Island

completeDrinking WaterCC
Federal contribution
$414,583
Federal share33%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 4, 2009
20102011
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Community of North Rustico
Construction start
Jul 30, 2010(actual)
Construction end
Jan 30, 2011(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2010
  • Construction end5 months lateforecast Sep 1, 2010