North Rustico Arena and Wellness Centre Construction
North Rustico, Prince Edward Island
Federal contribution
$3.8M
$3,800,452
Federal share40%
of $9.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 10, 2020
202120222023
Built
Approved 3 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of North Rustico
- Construction start
- Apr 1, 2021(actual)
- Construction end
- Feb 13, 2023(actual)
Against the original forecast
- Construction start7 months lateforecast Sep 8, 2020
- Construction end4 weeks lateforecast Jan 15, 2023
Also in North Rustico
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57012 in the federal list. How to read these figures.