Conception Bay Highway Sewermain
Bay Roberts, Newfoundland and Labrador
Federal contribution
$458,064
Federal share28%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 14, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of Bay Roberts
- Construction start
- Jun 1, 2011(actual)
- Construction end
- Oct 6, 2011(actual)
Against the original forecast
- Construction start19 months lateforecast Nov 1, 2009
- Construction end10 months lateforecast Nov 30, 2010
Also in Bay Roberts
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26652 in the federal list. How to read these figures.