Water and Sewer Upgrading
Bay Roberts, Newfoundland and Labrador
Federal contribution
$1.7M
$1,713,011
Federal share50%
of $3.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Bay Roberts
- Construction start
- Apr 23, 2018(actual)
- Construction end
- Nov 16, 2018(actual)
Against the original forecast
- Construction start3 weeks earlyforecast May 15, 2018
- Construction end4 months earlyforecast Mar 31, 2019