Water System Extension

Cape St. George, Newfoundland and Labrador

completeDrinking WaterCC
Federal contribution
$677,966
Federal share33%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 14, 2009
20102011
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Cape St. George
Construction start
Apr 25, 2011(actual)
Construction end
Sep 30, 2011(actual)

Against the original forecast

  • Construction start12 months lateforecast May 1, 2010
  • Construction end4.5 years earlyforecast Mar 31, 2016

Also in Cape St. George

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26665 in the federal list. How to read these figures.