Back to projects

Cape St. George Waterline Replacement

Cape St. George, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$181,267
Federal share40%

of $453.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 21, 2025
20242025
Built

Approved 21 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Cape St. George
Construction start
May 12, 2025(actual)
Construction end
Jun 6, 2025(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast Jun 16, 2025
  • Construction end3 months earlyforecast Aug 30, 2025

Also in Cape St. George

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67350 in the federal list. How to read these figures.