Cape St. George Waterline Replacement
Cape St. George, Newfoundland and Labrador
Federal contribution
$181,267
Federal share40%
of $453.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 21, 2025
20242025
Built
Approved 21 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Cape St. George
- Construction start
- May 12, 2025(actual)
- Construction end
- Jun 6, 2025(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Jun 16, 2025
- Construction end3 months earlyforecast Aug 30, 2025