Back to projects

New Water Supply system

Nain, Newfoundland and Labrador

completeDrinking WaterCC
Federal contribution
$4.1M
$4,140,657
Federal share33%

of $12.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 14, 2009
20102011201220132014
Built
Program
Building Canada Fund - Communities Component
Construction start
Jul 16, 2010(actual)
Construction end
Dec 17, 2013(actual)

Against the original forecast

  • Construction start9 months lateforecast Oct 1, 2009
  • Construction end3 months earlyforecast Mar 31, 2014

Also in Nain

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26670 in the federal list. How to read these figures.