Sandbanks Road Water Main Replacement (Nain)

Nain, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$1.3M
$1,330,381
Federal share39%

of $3.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
20202021
Built

Approved 4 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
Sep 17, 2020(actual)
Construction end
Oct 5, 2021(actual)

Against the original forecast

  • Construction start4 months earlyforecast Jan 7, 2021
  • Construction end5 weeks lateforecast Aug 31, 2021