Sandbanks Road Water Main Replacement (Nain)
Nain, Newfoundland and Labrador
Federal contribution
$1.3M
$1,330,381
Federal share39%
of $3.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
20202021
Built
Approved 4 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Inuit Community Government of Nain
- Construction start
- Sep 17, 2020(actual)
- Construction end
- Oct 5, 2021(actual)
Against the original forecast
- Construction start4 months earlyforecast Jan 7, 2021
- Construction end5 weeks lateforecast Aug 31, 2021
Also in Nain
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53946 in the federal list. How to read these figures.