Back to projects

Road Upgrading & Paving

Ferryland, Newfoundland and Labrador

completeHighways and RoadsCC Top Up
Federal contribution
$166,032
Federal share33%

of $498.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 14, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Town of Ferryland
Construction start
Nov 16, 2009(actual)
Construction end
Sep 10, 2010(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Oct 1, 2009
  • Construction end5 months lateforecast Apr 1, 2010

Also in Ferryland

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26672 in the federal list. How to read these figures.