Top Road Sewer Extension
Ferryland, Newfoundland and Labrador
Federal contribution
$152,620
Federal share50%
of $305.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Ferryland
- Construction start
- Jun 19, 2017(actual)
- Construction end
- Aug 14, 2017(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jun 1, 2017
- Construction end7 weeks earlyforecast Sep 30, 2017