Drinking Water System Improvements

Holyrood, Newfoundland and Labrador

completeDrinking WaterCC Top Up
Federal contribution
$115,444
Federal share6%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 14, 2009
2010201220142016
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Town of Holyrood
Construction start
May 15, 2011(actual)
Construction end
Mar 15, 2017(actual)

Against the original forecast

  • Construction start19 months lateforecast Oct 1, 2009
  • Construction end11 months lateforecast Mar 31, 2016