Water & Sewer System Upgrade

Placentia, Newfoundland and Labrador

completeDrinking WaterCC
Federal contribution
$1.1M
$1,090,501
Federal share33%

of $3.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 14, 2009
2010201220142016
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Placentia
Construction start
Apr 13, 2010(actual)
Construction end
Mar 15, 2017(actual)

Against the original forecast

  • Construction start6 months lateforecast Oct 15, 2009
  • Construction end11 months lateforecast Mar 31, 2016