Jerseyside Stormwater Collection
Placentia, Newfoundland and Labrador
Federal contribution
$725,004
Federal share40%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
2022202320242025
Built
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Placentia
- Construction start
- Sep 1, 2023(actual)
- Construction end
- Oct 6, 2025(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 1, 2023
- Construction end4 months lateforecast Jun 15, 2025
Also in Placentia
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61153 in the federal list. How to read these figures.