Water Treatment Facility
Marystown, Newfoundland and Labrador
Federal contribution
$4.0M
$3,968,429
Federal share33%
of $12.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 14, 2009
2010201120122013
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Marystown
- Construction start
- May 21, 2010(actual)
- Construction end
- Jun 27, 2013(actual)
Against the original forecast
- Construction start8 months lateforecast Oct 1, 2009
- Construction end15 months lateforecast Mar 31, 2012