Water and Sewer Upgrade
Marystown, Newfoundland and Labrador
Federal contribution
$927,397
Federal share50%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Marystown
- Construction start
- May 1, 2017(actual)
- Construction end
- Dec 1, 2017(actual)
Against the original forecast
- Construction start4 weeks lateforecast Apr 1, 2017
- Construction end2 months lateforecast Sep 22, 2017
Also in Marystown
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47059 in the federal list. How to read these figures.