Schedule

Announced and approvedMay 14, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Town of Labrador City
Construction start
Jun 15, 2009(actual)
Construction end
Jul 31, 2010(actual)

Against the original forecast

  • Construction start4 months earlyforecast Oct 1, 2009
  • Construction end5 months lateforecast Feb 28, 2010