Sanitary Sewer Upgrading/Roads
Labrador City, Newfoundland and Labrador
Federal contribution
$636,294
Federal share33%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 14, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of Labrador City
- Construction start
- Jun 15, 2009(actual)
- Construction end
- Jul 31, 2010(actual)
Against the original forecast
- Construction start4 months earlyforecast Oct 1, 2009
- Construction end5 months lateforecast Feb 28, 2010
Also in Labrador City
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26717 in the federal list. How to read these figures.