Drake Wastewater Treatment Plant Upgrades

Labrador City, Newfoundland and Labrador

completeWastewaterSCF
Federal contribution
$1.1M
$1,107,739
Federal share33%

of $3.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2018
20192020202120222023
Built

Approved 2 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Labrador City
Construction start
Apr 1, 2022(actual)
Construction end
Jan 24, 2023(actual)

Against the original forecast

  • Construction start2 months earlyforecast Jun 3, 2022
  • Construction end2 months earlyforecast Mar 31, 2023