Stormwater and Sewage System Renewal-Commercial St.
Federal contribution
$252,063
Federal share33%
of $756.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 30, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of Berwick
- Construction start
- Jul 12, 2010(actual)
- Construction end
- Sep 30, 2011(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 31, 2010
- Construction end4 months lateforecast Jun 15, 2011
Also in Berwick
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26733 in the federal list. How to read these figures.