Kings Mutual Century Centre (aka Apple Dome) Phase 2 Construction

Berwick, Nova Scotia

completeRecreationSCF
Federal contribution
$1.6M
$1,600,000
Federal share30%

of $5.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 16, 2017
20182019
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Berwick
Construction start
Oct 23, 2017(actual)
Construction end
Oct 31, 2019(actual)

Against the original forecast

  • Construction start7 months lateforecast Apr 1, 2017
  • Construction end5 months earlyforecast Mar 31, 2020