Back to projects

2009 Storm Water Control & Sidewalk

Charlottetown, Prince Edward Island

completeWastewaterCC
Federal contribution
$996,828
Federal share31%

of $3.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 4, 2009
20102011
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Charlottetown
Construction start
Jun 16, 2009(actual)
Construction end
Dec 31, 2010(actual)

Against the original forecast

  • Construction end16 months lateforecast Aug 31, 2009

Also in Charlottetown