Back to projects

University Ave Traffic Flow Improvements

Charlottetown, Prince Edward Island

completeHighways and RoadsCC Top Up
Federal contribution
$2.1M
$2,100,000
Federal share33%

of $6.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 4, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
City of Charlottetown
Construction start
Nov 9, 2009(actual)
Construction end
Dec 1, 2010(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Sep 15, 2009
  • Construction end2 months lateforecast Oct 1, 2010

Also in Charlottetown

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26784 in the federal list. How to read these figures.