Equilzation Tank on Brudenell Sequencing Batch Reactor

Charlottetown, Prince Edward Island

completeWastewaterCC
Federal contribution
$26,667
Federal share33%

of $80.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
201120122013201420152016
Built

Approved 5.9 years before the announcement.

Program
Building Canada Fund - Communities Component
Construction start
Feb 1, 2012(actual)
Construction end
Oct 15, 2013(actual)

Against the original forecast

  • Construction end10 months lateforecast Dec 7, 2012

Also in Charlottetown

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26797 in the federal list. How to read these figures.