PEI BioCommons Research Park Infrastructure

Charlottetown, Prince Edward Island

completeHighways and RoadsCC
Federal contribution
$984,200
Federal share33%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 4, 2009
201020112012
Built
Program
Building Canada Fund - Communities Component
Construction start
Jul 26, 2010(actual)
Construction end
Apr 30, 2012(actual)

Against the original forecast

  • Construction start3 months lateforecast Apr 15, 2010
  • Construction end7 months lateforecast Oct 15, 2011

Also in Charlottetown

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26865 in the federal list. How to read these figures.