Looping of Water Mains
Federal contribution
$53,541
Federal share33%
of $160.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Village of Elbow
- Construction start
- May 27, 2010(actual)
- Construction end
- Jun 14, 2010(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 1, 2010
- Construction end10 months earlyforecast Mar 31, 2011
Also in Elbow