New Water Intake and Supply System at Elbow

Elbow, Saskatchewan

completeDrinking WaterCWWF
Federal contribution
$975,000
Federal share50%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 2, 2017
2018
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
SaskWater
Construction start
Apr 30, 2017(actual)
Construction end
Jun 26, 2018(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast Jun 1, 2017
  • Construction end9 months earlyforecast Mar 31, 2019