New Water Intake and Supply System at Elbow
Federal contribution
$975,000
Federal share50%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 2, 2017
2018
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- SaskWater
- Construction start
- Apr 30, 2017(actual)
- Construction end
- Jun 26, 2018(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Jun 1, 2017
- Construction end9 months earlyforecast Mar 31, 2019