Waterline-storm sewer replacement & roadway repair
Federal contribution
$1.6M
$1,591,527
Federal share33%
of $4.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Melfort
- Construction start
- Sep 2, 2009(actual)
- Construction end
- Aug 22, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 22, 2009
- Construction end19 months earlyforecast Mar 31, 2013
Also in Melfort
- Melfort Water Treatment Plant Upgrades$2.8M
- City of Melfort - Melfort Landfill Decommissioning - Progressive Closure of the Active Landfill$984.4K
- Main Sewage Lift Station and Pumping Upgrade$433.4K
- Melfort and District Curling Club - Rink Roof Retrofit & Ice Plant Replacement$169.9K
- Walking Trails$145.6K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26899 in the federal list. How to read these figures.