Melfort and District Curling Club - Rink Roof Retrofit & Ice Plant Replacement
Federal contribution
$169,894
Federal share40%
of $424.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 6, 2022
20232024
Built
Approved 3 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Melfort and District Curling Club
- Construction start
- Oct 3, 2022(actual)
- Construction end
- Mar 29, 2024(actual)
Against the original forecast
- Construction start6 months lateforecast Apr 9, 2022