Back to projects

Water Treatment Plant and Pipeline

Carlyle, Saskatchewan

completeDrinking WaterCC
Federal contribution
$1.4M
$1,425,000
Federal share33%

of $4.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
201020112012
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Carlyle
Construction start
Nov 5, 2009(actual)
Construction end
Aug 31, 2012(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 22, 2009
  • Construction end7 months earlyforecast Mar 31, 2013

Also in Carlyle

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26955 in the federal list. How to read these figures.