Lagoon Aeration Upgrade
Federal contribution
$447,500
Federal share50%
of $895.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 11, 2017
20172018
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Carlyle
- Construction start
- Jun 26, 2017(actual)
- Construction end
- Nov 26, 2018(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 15, 2017
- Construction end5 weeks earlyforecast Dec 31, 2018
Also in Carlyle
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48414 in the federal list. How to read these figures.