Water Treatment Plant

Pangman, Saskatchewan

completeDrinking WaterCC
Federal contribution
$288,533
Federal share33%

of $865.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
2010201120122013
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Village of Pangman
Construction start
Jul 19, 2010(actual)
Construction end
Nov 26, 2012(actual)

Against the original forecast

  • Construction start13 months lateforecast Jun 22, 2009
  • Construction end16 months earlyforecast Mar 31, 2014

Also in Pangman

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27029 in the federal list. How to read these figures.