Village of Pangman Lagoon Expansion
Federal contribution
$371,807
Federal share40%
of $929.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 6, 2023
2024
Built
Approved 3 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Pangman
- Construction start
- Aug 9, 2024(actual)
- Construction end
- Oct 31, 2024(actual)
Against the original forecast
- Construction end2 months earlyforecast Dec 31, 2024
Also in Pangman
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67523 in the federal list. How to read these figures.