Lagoon Upgrade

Moosomin, Saskatchewan

completeWastewaterCC
Federal contribution
$615,801
Federal share33%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2009
2010201120122013
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Moosomin
Construction start
Jun 1, 2012(actual)
Construction end
Mar 27, 2013(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Apr 15, 2012
  • Construction end12 months earlyforecast Mar 31, 2014

Also in Moosomin

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27033 in the federal list. How to read these figures.