Town of Moosomin Water Treatment Plant Upgrades

Moosomin, Saskatchewan

underwayDrinking WaterGIS
Federal contribution
$5.5M
$5,492,190
Federal share40%

of $13.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 27, 2022
2023202420252026
BuiltForecast

Approved 8 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Moosomin
Construction start
Sep 5, 2023(actual)
Construction end
Mar 31, 2026(forecast)

Against the original forecast

  • Construction start4 months lateforecast Apr 28, 2023