Organized Hamlet of Maymont - Deep Water Line
Federal contribution
$37,625
Federal share33%
of $112.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
2010
Built
Approved 2 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Village of Meota
- Construction start
- Apr 28, 2010(actual)
- Construction end
- Jul 10, 2010(actual)
Against the original forecast
- Construction start10 months lateforecast Jun 22, 2009
- Construction end2.7 years earlyforecast Mar 31, 2013
Also in Meota
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27055 in the federal list. How to read these figures.